Report for July 16

Report Date
July 2016

Achievements

  • Project brief was completed and signed off by project team members but was rejected at wis
  • A meeting was held with stakeholders and a way forward agreed - project brief being resubmitted this week

 

Issues

  • Project brief was initially rejected as Service Management said that they could provide the service required rather than move it into APPS. As PM received conflicting information as how to proceed it was escalated to wis who asked for a meeting between all the representatives (specifically Mark Lang, Alain Forrester and Ana Heyn) to discuss the current issues and to decide on the best approach to move forward with this project. It was then agreed to take forward under APPS. It was agreed at the meeting that the project brief could now be considered approved and build could continue. Project brief to be resubmitted to WIS

 

Next Steps

  • Project brief resubmitted
  • Build signoff

Milestones

5-Aug-2016Planning
16-Aug-2016Build
19-Aug--2016Integration/Acceptance
29-Aug--2016Deploy to Live
29-Aug--2016Synch live data
12-Sep-2016DSOR
19-Sep-2016Close
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
40.0 days
Activity this month
10.0 days
Activity this year
10.0 days
Activity to date
10.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
30.0 days

Project Info

Project
TEL039 WebPA Migration
Code
TEL039
Programme
ISG - Technology Enhanced Learning (TEL)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
13-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Feb-2017
Overall Priority
Normal
Category
Discretionary