Organisation

Methodology Compliance

 

Methodology Stage

Standard Stage Sign-Off

Project Approach

Planning

Approval by Project Manager, Project Sponsor and IS Applications Management Team (WIS)

 

Business Analysis

Peer Project Analysis Review (PPAR)

 

System Analysis & Design

Peer Project Design Review (PPDR)

 

Build

Peer Project Build Review (PPBR)

 

Integration

Peer Project Integration Review (PPIR)

 

Acceptance

Acceptance Sign-Off Review (ASOR)

 

Deployment

Deployment Sign-Off Review (DSOR)

 

Closure

Closure Review and Approval by Project Manager, Project Sponsor and IS Applications Management Team

 

Resources

Resource Estimates and Costs

Original Estimate

Revised Estimate

Reason for Revision

IS Applications Staff Resource

 

 

 

 

 

Support Group Staff Resource

 

 

 

 

 

College Staff and Student Resource

 

 

 

 

 

Hardware Software and Service Costs

 

 

 

 

 

 

Post Project Resource Estimates

Original Estimate

Revised Estimate

Reason for Revision

IS Applications Staff Resource

 

 

 

 

 

Support Group Staff Resource

 

 

 

 

 

College Staff and Student Resource

 

 

 

 

 

Hardware Software and Service Costs

 

 

 

 

 

 

Dedicated Project Team?

 

 

Out of Hours Working

 

Additional Information

Project Info

Project
Migration of MVM UG MBChB to PebblePad
Code
TEL024
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
Sue Woodger
Project Sponsor
Jo Spiller
Current Stage
Close
Status
Closed
Start Date
14-Apr-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Oct-2015
Programme Priority
10
Overall Priority
Normal
Category
Discretionary