Update - week ending 12/06
This week's work encompassed the following:
- All work completed and tested in DEV
- Sign-off of the Build stage
- Database elements of solution deployed into TEST
- Revised milestones agredd with stakeholders and approved with WIS
- Additional effort (to cover Moodle changes) approved
The task of promoting the BI elements to TEST has been requested and is expected to be done 15/06. User testing can then be commenced.