Update - week ending 12/06

This week's work encompassed the following:

  • All work completed and tested in DEV
  • Sign-off of the Build stage
  • Database elements of solution deployed into TEST
  • Revised milestones agredd with stakeholders and approved with WIS
  • Additional effort (to cover Moodle changes) approved

The task of promoting the BI elements to TEST has been requested and is expected to be done 15/06. User testing can then be commenced.

David Watters, IS Applications

Project Info

Project
TELS Management Information
Code
TEL021
Programme
ISG - Technology Enhanced Learning (TEL)
Project Manager
David Watters
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
15-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Dec-2015
Programme Priority
7
Overall Priority
Normal
Category
Discretionary