w/c 21st October 2019

  • Email issue appears to have been resolved 
  • SSO 
    • After discussions within the technical project team, it was agreed that the existing SSO configuration was acceptable by incorporating the double log in process regarding 
      • confirmation of user account within the application 
      • confirmation of an active EASE user
    • Final tests regarding visitor accounts scheduled for next week 

Project Info

Project
Privacy Impact Assessment Tool (GDPR Requirement)
Code
STU257
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Renate Gertz
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
07-Aug-2017
Planning Date
06-Oct-2017
Delivery Date
03-Jul-2019
Close Date
12-Dec-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation