Report for May 2017
- Report Date
- May 2017
Achievements in Last Period
- Closure report written and distributed for review. All feedback received has been incorporated.
- Agreement on closure milestone and report at team meeting 08-Jun-17.
Issues
- CLOSED: Delayed closure meeting as Business Lead unavailable due to British Airways IT failure. Closure meeting was re-planned for Thursday 08/06/2017.
Next Steps
- Finalise project closure.
RAG Commentary
ISSUE - Delay to closure meeting due to 1) BA IT Failure.
- Approved budget
- 256.0 days
- Activity this month
- 3.0 days
- Activity this year
- 132.0 days
- Activity to date
- 267.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days