Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • Deploy PG changes to LIVE - Complete
  • Deployment sign off for PG and Database deployments - Complete
  • XCRI-CAP is out of scope for this project and will be put into the next CAM project which is starting immediately on STU251's closure

 

Issues

  • Closure date to be moved from 12/07/17 to 26/05/17 as XCRI-CAP is out of scope. This scope change / closure date change has put the project status into RED. Scope change has been agreed by the project team and sponsor. Closure date change to be agreed by project team

 

Next Steps

  • Replan and agree milestones to close at the end of May
  • Distribute closure report
  • Closure Meeting
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
RED
Overall
RED
RAG Commentary
Change. Removal of XCRI-CAP from scope and to include this into next project. Closure date to be moved from 12/07/17 to 26/05/17 as a result.
Change Status
Activity
Approved budget
251.0 days
Activity this month
3.0 days
Activity this year
129.0 days
Activity to date
264.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CAM - Enhancements to UG and PG Degree Finders
Code
STU251
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Start Date
04-Dec-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Jun-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary