Report for April 2017
- Report Date
- April 2017
Achievements in Last Period
- Deploy PG changes to LIVE - Complete
- Deployment sign off for PG and Database deployments - Complete
- XCRI-CAP is out of scope for this project and will be put into the next CAM project which is starting immediately on STU251's closure
Issues
- Closure date to be moved from 12/07/17 to 26/05/17 as XCRI-CAP is out of scope. This scope change / closure date change has put the project status into RED. Scope change has been agreed by the project team and sponsor. Closure date change to be agreed by project team
Next Steps
- Replan and agree milestones to close at the end of May
- Distribute closure report
- Closure Meeting
- Approved budget
- 251.0 days
- Activity this month
- 3.0 days
- Activity this year
- 129.0 days
- Activity to date
- 264.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days