November 2013
- Report Date
- November 2013
Achievements in last period
- Set up series of meetings in Nov/Dec with the 3 User Groups to review business processes, determine requirements and priority.
Issues
n/a
Next Steps
- Complete 2nd round User Groups meetings to identify requirements and priority.
- Complete Brief for the IT Tool
- Approved budget
- 190.0 days
- Activity this month
- 2.9 days
- Activity this year
- 11.5 days
- Activity to date
- 11.5 days
- Estimate to complete current year
- 176.8 days
- Estimate to complete future years
- 0.0 days