- Report Date
- August 2014
Achievements in last period
- BI Suite was deployed and all documentation was completed.
- DSOR held.
- Schools users and External Examiners data were imported into EERS end August.
Issues
Next Steps
- Approved budget
- 295.0 days
- Activity this month
- 5.5 days
- Activity this year
- 5.5 days
- Activity to date
- 294.4 days
- Estimate to complete current year
- 0.6 days
- Estimate to complete future years
- 0.0 days
This article was published on