August 2014

Report Date
August 2014

Achievements in last period

  • BI Suite was deployed and all documentation was completed.
  • DSOR held. 
  • Schools users and External Examiners data were imported into EERS end August. 

Issues

  • n/a

Next Steps

  • Close
12-Sep-2014Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
295.0 days
Activity this month
5.5 days
Activity this year
5.5 days
Activity to date
294.4 days
Estimate to complete current year
0.6 days
Estimate to complete future years
0.0 days

Project Info

Project
External Examiner Online Reporting System
Code
STU235
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Tina Harrison
Current Stage
Close
Status
Closed
Start Date
04-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Sep-2014
Programme Priority
7
Overall Priority
Higher
Category
Compliance