Achievements in last period

  • Completed last 2 terations 9 and 10
  • Deployed to Live IT Tool for EE Reporting System EERS

Issues

Next Steps

  • Progress with BI Suite and documentation
  • Deployment Sign off Review and close

 

20-Aug-2014DSOR
12-Sep-2014Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
295.0 days
Activity this month
37.0 days
Activity this year
289.0 days
Activity to date
289.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
6.0 days

Project Info

Project
External Examiner Online Reporting System
Code
STU235
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Tina Harrison
Current Stage
Close
Status
Closed
Start Date
04-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Sep-2014
Programme Priority
7
Overall Priority
Higher
Category
Compliance