June 2014
- Report Date
- June 2014
Achievements in last period
- Completed iterations 7 and 8
- Completed demo of BI Suite changes to User Reps, and end to end process to Board and Pilot Schools
Issues
- n/a
Next Steps
- Progress with build final iterations 9 and 10
| 30-Jul-2014 | Release 3 - final iteration 10 |
| 13-Aug-2014 | Maintenance completed |
| 20-Aug-2014 | DSOR |
| 12-Sep-2014 | Closure |
- Approved budget
- 295.0 days
- Activity this month
- 60.0 days
- Activity this year
- 251.9 days
- Activity to date
- 251.9 days
- Estimate to complete current year
- 36.6 days
- Estimate to complete future years
- 7.0 days