June 2014

Report Date
June 2014

Achievements in last period

  • Completed iterations 7 and 8
  • Completed demo of BI Suite changes to User Reps, and end to end process to Board and Pilot Schools

Issues

  • n/a

Next Steps

  • Progress with build final iterations 9 and 10

 

30-Jul-2014Release 3 - final iteration 10
13-Aug-2014Maintenance completed
20-Aug-2014DSOR
12-Sep-2014Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
295.0 days
Activity this month
60.0 days
Activity this year
251.9 days
Activity to date
251.9 days
Estimate to complete current year
36.6 days
Estimate to complete future years
7.0 days

Project Info

Project
External Examiner Online Reporting System
Code
STU235
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Tina Harrison
Current Stage
Close
Status
Closed
Start Date
04-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Sep-2014
Programme Priority
7
Overall Priority
Higher
Category
Compliance