Report for March 2014

Report Date
March 2014

Achievements in Last Period

  • Fix for student helpers tested and implemented into LIVE
  • Deployment sign-off completed
  • Project closure prepared and approved
Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
75.0 days
Activity this month
1.0 day
Activity this year
75.0 days
Activity to date
75.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrade SAGE to CF9
Code
STU234
Programme
Student Services (STU)
Project Manager
David Watters
Project Sponsor
Steve Norman
Current Stage
Close
Status
Closed
Start Date
07-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Apr-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance