Report for February 2014
- Report Date
- February 2014
Achievements in Last Period
- Issue reported by Careers staff (wrt student helpers) addressed
- Revised milestones prepared
Issues
- Staff in Careers reported problems with student helper accounts
Next Steps
- Fix for student helpers to be tested
- Deployment sign-off arranged for mid-March
- Project closure to be prepared and submitted for approval
| 18-Mar-2014 | System Deployment sign-off |
| 28-Mar-2014 | Project Closure |
- Approved budget
- 68.0 days
- Activity this month
- 2.6 days
- Activity this year
- 74.0 days
- Activity to date
- 74.0 days
- Estimate to complete current year
- 0.5 days
- Estimate to complete future years
- 0.0 days