Report for January 2014

Report Date
January 2014

Achievements in Last Period

  • One more issue reported by Careers staff addressed and solution applied to TEST

Issues

  • Problems reported adding new staff users to SAGE ADMIN
  • Testers in Careers reported problems with EASE TEST accounts

Next Steps

  • Outstanding milestones to be approved
  • Deployment milestone mid-February
  • Project closure to be prepared and submitted for approval

 

Milestones to be updated and agreed

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
68.0 days
Activity this month
2.9 days
Activity this year
71.4 days
Activity to date
71.4 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrade SAGE to CF9
Code
STU234
Programme
Student Services (STU)
Project Manager
David Watters
Project Sponsor
Steve Norman
Current Stage
Close
Status
Closed
Start Date
07-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Apr-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance