Week ending 5th October 2012 |
- Deployment signed off by stakeholders
- DSOR completed and submitted to WIS
- Completion report signed off by stakeholders
- Completion report submitted to WIS
- Project closed
|
David Watters |
09-Oct-2012 |
Week ending 28th September 2012 |
- Upgraded application deployed into LIVE
- No issues reported by users
- Completion report prepared ahead of distribution to stakeholders
|
David Watters |
02-Oct-2012 |
Week ending 21st September 2012 |
- Date for deployment arranged with Careers and IS Apps staff
- Service Announcement published
- Changes arranged with ITI Unix
|
David Watters |
02-Oct-2012 |
Week ending 14th September 2012 |
- User testing completed successfully by Careers
- Initial arrangements made for deployment into LIVE
|
David Watters |
02-Oct-2012 |
Week ending 24/08/12 |
- Testing of CCTS still not completed - staff not available in Careers
- Outstanding milestones revised and submitted to WIS for approval
- Arrangements for leave period made with Programme Manager
|
David Watters |
24-Aug-2012 |
Week ending 17/08/12 |
- New milestones approved by WIS; website updated
- No progress on user testing this week
|
David Watters |
17-Aug-2012 |
Week ending 10th August 2012 |
- ColdFusion 9 version of CCTS application promoted to TEST environment
- Discussions held with Programme Manager about SAGE applications
- PICCL submitted to WIS for revised milestones because of delay to UAT
|
David Watters |
10-Aug-2012 |