Project journal

Title Description Author Post date
Week ending 5th October 2012
  • Deployment signed off by stakeholders
  • DSOR completed and submitted to WIS
  • Completion report signed off by stakeholders
  • Completion report submitted to WIS
  • Project closed
David Watters 09-Oct-2012
Week ending 28th September 2012
  • Upgraded application deployed into LIVE
  • No issues reported by users
  • Completion report prepared ahead of distribution to stakeholders
David Watters 02-Oct-2012
Week ending 21st September 2012
  • Date for deployment arranged with Careers and IS Apps staff
  • Service Announcement published
  • Changes arranged with ITI Unix
David Watters 02-Oct-2012
Week ending 14th September 2012
  • User testing completed successfully by Careers
  • Initial arrangements made for deployment into LIVE
David Watters 02-Oct-2012
Week ending 24/08/12
  • Testing of CCTS still not completed - staff not available in Careers
  • Outstanding milestones revised and submitted to WIS for approval
  • Arrangements for leave period made with Programme Manager
David Watters 24-Aug-2012
Week ending 17/08/12
  • New milestones approved by WIS; website updated
  • No progress on user testing this week
David Watters 17-Aug-2012
Week ending 10th August 2012
  • ColdFusion 9 version of CCTS application promoted to TEST environment
  • Discussions held with Programme Manager about SAGE applications
  • PICCL submitted to WIS for revised milestones because of delay to UAT
David Watters 10-Aug-2012

Project Info

Project
ColdFusion Upgrade: Careers
Code
STU204
Programme
Student Services (STU)
Project Manager
David Watters
Project Sponsor
Steve Norman
Current Stage
Close
Status
Closed
Start Date
31-May-2011
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Sep-2012
Programme Priority
3
Overall Priority
Normal
Category
Compliance

Documentation