Report for February 2017

Report Date
February 2017

Achievements in Last Period

  • Hardware Import established and set up as monthly job

Issues

  • None reported

Next Steps​

  • Prepare for deployment of Change Release in mid-March

 

Milestones

17-Mar-2017 Deploy Chg/Rel/SACM Deliver
31-Mar-2017 DSOR Deliver
07-Apr-2017 Project Closed Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
50.0 days
Activity this month
1.5 days
Activity this year
48.2 days
Activity to date
48.2 days
Estimate to complete current year
1.8 days
Estimate to complete future years
0.0 days

Project Info

Project
UniDesk for Durham University
Code
SMI017
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
22-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017