June 2015

Report Date
June 2015

 

Achievements in Last Period

  • separate Edinburgh into its own environment - done
  • TopDesk on-site to start analysis (end of June) - in place for w/c 29th

Issues

  • no issues of note
  • no medium or high risks

Next Steps

  • recommendations report

Milestones

 

10-Jul-2015Recommendations Report
17-Jul-2015Project Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
30.0 days
Activity this month
18.0 days
Activity this year
23.0 days
Activity to date
23.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Review of UniDesk Infrastructure
Code
SMI011
Programme
ISG - IT Service Management (SMI)
Project Manager
Maurice Franceschi
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Aug-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary