December 2013

Report Date
December 2013

2013/14 overall funded budget (total, apps/service management) - 150 (105/45) 2013/14 effort so far (total, apps/service management)                 - 52 ( 41/ 11) 2013/14 estimate to complete (total, apps/service management)   - 33 ( 24/  9)

Achievements in Last Period

  • CSV -> Hardware Holding Table built (using MCC for Edinburgh)

Issues

  • Risk from additional import nightly hopefully resolved by Person Import Improvement work
  • Risk of unusable CI relationships view resovled by TreeWalk development
  • Conflict in all insititutuions with other priority work resolved by new milestones agreed with the board

Next Steps

  • Complete build of CSV -> Holding Table extracts for all partners
  • UAT of CMDB process by end of Jan
  • UAT of Hardware Holding Table data import by end of Jan
  • UAT of TreeWalk by end of Jan
  • UAT of Person Import Improvement by end of Jan
  • Review of all implementation plans by end of Jan

 

Milestones

17-Jan-201413-Dec-2013Sign-Off of Configuration and Build of UniDesk CMDB Process and Extract of Hardware DataBuild
31-Jan-201424-Jan-2014Acceptance Sign-Off of Person Import ImprovementAccept
31-Jan-201424-Jan-2014Acceptance Sign-Off of Tree WalkAccept
31-Jan-201424-Jan-2014Acceptance Sign-Off of CMDB amd Extract Process for All PartnersAccept
14-Feb-201414-Feb-2014Sign-Off of any other Data Imports that are needed (Software only expected)Accept
28-Feb-201405-Dec-2013Delivery of CMDB Process and Configured DatabaseDeliver
05-Mar-201405-Mar-2014Deployment Sign-OffDeliver
12-Mar-201419-Dec-2013Project ClosureClose

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
105.0 days
Activity this month
10.0 days
Activity this year
51.0 days
Activity to date
56.0 days
Estimate to complete current year
49.0 days
Estimate to complete future years
0.0 days