May 2014

Report Date
May 2014

Funded Budget  

2012/13 overall funded budget (total, apps/service management) -      8 days  (5/3) 2012/13 actual effort (total, apps/service management)                   -      8 days  (3/5)

=

2013/14 overall funded budget (total, apps/service management) - 150  (105/45) 2013/14 effort so far (total, apps/service management)                    -   131   ( 112/ 19) 2013/14 estimate to complete (total, apps/service management)      -    1   ( 1/  1)So the project is delivering under 18 days of the funded budget approved by the UniDesk Project Board.

Overview

CMDB has been delivered to Edinburgh UniDesk, with our partners' delivery due in early June.

Achievements in Last Period

  • UAT sign-off Edinburgh of CMDB, H/W Import and TreeWalk
  • UAT sign-off Abertay of CMDB, H/W Import and TreeWalk
  • Delivery to Edinburgh

Issues

  • none

Next Steps

  • Delivery to Abertay, St ANdrews and Sheffield
  • Depoyment Sign-Off
  • Closure  

Milestones

05-Jun-2014Delivery of CMDB Process and Configured Database to PartnersDeliverview
12-Jun-2014Deployment Sign-OffDeliverview
19-Jun-2014Project ClosureCloseview

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
108.0 days
Activity this month
10.0 days
Activity this year
107.0 days
Activity to date
112.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days