May 2014
- Report Date
- May 2014
Funded Budget
2012/13 overall funded budget (total, apps/service management) - 8 days (5/3) 2012/13 actual effort (total, apps/service management) - 8 days (3/5)
=
2013/14 overall funded budget (total, apps/service management) - 150 (105/45) 2013/14 effort so far (total, apps/service management) - 131 ( 112/ 19) 2013/14 estimate to complete (total, apps/service management) - 1 ( 1/ 1)So the project is delivering under 18 days of the funded budget approved by the UniDesk Project Board.
Overview
CMDB has been delivered to Edinburgh UniDesk, with our partners' delivery due in early June.
Achievements in Last Period
- UAT sign-off Edinburgh of CMDB, H/W Import and TreeWalk
- UAT sign-off Abertay of CMDB, H/W Import and TreeWalk
- Delivery to Edinburgh
Issues
- none
Next Steps
- Delivery to Abertay, St ANdrews and Sheffield
- Depoyment Sign-Off
- Closure
Milestones
| 05-Jun-2014 | Delivery of CMDB Process and Configured Database to Partners | Deliver | view |
| 12-Jun-2014 | Deployment Sign-Off | Deliver | view |
| 19-Jun-2014 | Project Closure | Close | view |
- Approved budget
- 108.0 days
- Activity this month
- 10.0 days
- Activity this year
- 107.0 days
- Activity to date
- 112.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days