April 2014
- Report Date
- April 2014
Funded Budget
2012/13 overall funded budget (total, apps/service management) - 8 days (5/3) 2012/13 actual effort (total, apps/service management) - 8 days (3/5)
= 2013/14 overall funded budget (total, apps/service management) - 150 (105/45) 2013/14 effort so far (total, apps/service management) - 114 ( 97/ 17) 2013/14 estimate to complete (total, apps/service management) - 11 ( 7/ 4)
Overview
Having review the project plan with the project team who are now all returned from annual leave and paternity leave, with the directive from the project board to close the project as soon as possible in May, given current resource availability and the need to complete UAT with the users (some of who have issues accessing TEST) the project team is confident in the new milestones below to complete UAT, deliver and close.
Complete UAT 13/5, deliver the week after, close the week after.
The sign-offs from Edinburgh and Abertay will be sufficient as stated by the project board.
Achievements in Last Period
- Integration testing of TreeWalk and CMDB import
Issues
- none
Next Steps
- UAT sign-off Edinburgh of CMDB, H/W Import and TreeWalk
- UAT sign-off Abertay of CMDB, H/W Import and TreeWalk
Milestones
| 13-May-2014 | 30-Apr-2014 | Acceptance Sign-Off of Person Import Improvement (Service Management) | Accept |
| 13-May-2014 | 30-Apr-2014 | Acceptance Sign-Off of CMDB Configuration (Abertay) | Accept |
| 13-May-2014 | 30-Apr-2014 | Acceptance Sign-Off of Tree Walk (Edinburgh) | Accept |
| 13-May-2014 | 30-Apr-2014 | Acceptance Sign-Off of CMDB Configuration and Hardware Extract Process (Edinburgh) | Accept |
| 13-May-2014 | 30-Apr-2014 | Acceptance Sign-Off of Software Extract Process (Abertay) | Accept |
| 13-May-2014 | 30-Apr-2014 | Acceptance Sign-Off of CMDB Configuration (St Andrews) - Not Essential | Accept |
| 20-May-2014 | 07-May-2014 | Delivery of CMDB Process and Configured Database | Deliver |
| 23-May-2014 | 14-May-2014 | Deployment Sign-Off | Deliver |
| 28-May-2014 | 21-May-2014 | Project Closure | Close |
- Approved budget
- 108.0 days
- Activity this month
- 3.0 days
- Activity this year
- 97.0 days
- Activity to date
- 102.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 0.0 days