Organisation

Work/Task Breakdown

Task Estimate (days) Team
DevTech Consultation with Desktop Services Risk 1 is not having a way of automatically deploying the system to HSS desktops. Iain Fiddes has therefore recommended that the first task should be to consult with Desktop Services to confirm that they can do this 2 DevTech
Building the new OCS system on the VM    
o   Technical proposal (TAD, BRD, Operational Specification) 5 DevTech
o   Build 5 DevTech
o   Config, preparation and Validation 5 DevTech
o   There is no expectation of disaster recovery  - will need a back-up but no DR – will restore from tape 0 N/A
o   Contingency = 10 days 10 DevTech
Handover to IS Apps  Production Management 0.5 DevTech
  0.5 TechMan
Project Management 4 Project Services
Business Analysis TBC  
     
TOTAL HSS005 30  
TOTAL Expected 20  

Resources, Skills and Costs

Team Actual HSS005 Estimate SCE017 Variance  
Project Services 4 4 0
Development Technology 25.5 (not confirmed) 15.5 - 39.22%
Technology Management 0.5 0.5 n/a
Total 30 (100%) 20 (66.66%) - 33.34%

 

Project Governance

 

 

Project Stakeholders

(Please copy and paste from Stakeholder List)

 

Project Estimations

(Please attach/link from Estimation Log)

 

Project Info

Project
Deployment of Open Computer and Software Inventory
Code
SCE017
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Victoria Dishon
Current Stage
Initiate
Status
In Progress
Project Classification
Transform
Start Date
27-Jan-2020
Planning Date
21-Feb-2020
Delivery Date
24-Apr-2020
Close Date
08-May-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Plan