Report for December 2019

Report Date
December 2019

Achievements this period

  • The project went live on the  on the 9th December.

Issues

  • None.

Next Steps

  • One outstanding activity has yet to be concluded in relation  to the possible provisioning of a GEOLEARNS database, standby solution.
  • The business having been presented with a number of options and are to advise on their favoured approach should a standby solution be pursued. 
  • To bring project closure.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
84.0 days
Activity this month
7.5 days
Activity this year
42.0 days
Activity to date
67.5 days
Estimate to complete current year
4.5 days
Estimate to complete future years
0.0 days

Project Info

Project
GeoSciences Databases Upgrade and Migration
Code
SCE015
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Victoria Dishon
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
29-Mar-2019
Planning Date
19-Jul-2019
Delivery Date
11-Dec-2019
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Discretionary