Report for November 2019

Report Date
November 2019

Achievements this period

  • Agreed DBA privileges and successfully re-tested connections.
  • Finalised build required for LIVE deployment, including TMS backups.
  • Completed Technical Architecture Document (TAD).
  • Drafted Operational Level Agreement (OLA).

Issues

  • Strike action has meant that a number of JIRA issues remain open. These need to be reviewed but are believed not to be of severity that would prevent the project from going live. 
  • A target deployment date of the 9th December awaits Go-CAB approval.

Next Steps

  • Ensure deployment checklist is complete.
  • Operational Level Agreement to be signed-off by Project Sponsor.
  • Undertake deployment and bring project to closure.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project has been re-planned outside of the change freeze. Deployment date not yet confirmed due to non-availability of change/project resource as a consequence of strike action.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
84.0 days
Activity this month
5.5 days
Activity this year
34.5 days
Activity to date
60.5 days
Estimate to complete current year
9.5 days
Estimate to complete future years
0.0 days

Project Info

Project
GeoSciences Databases Upgrade and Migration
Code
SCE015
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Victoria Dishon
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
29-Mar-2019
Planning Date
19-Jul-2019
Delivery Date
11-Dec-2019
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Discretionary