Deployment

Deployment Strategy

 

Dependencies

 

Communication

 

Deployment Checklists

Application checklist

 

Component

Success Criteria

Project Stage Required (Agile)

OK (Y/N)Reviewed by (date)Outdstanding Actions (Who)

Implementation Plan

Feedback from previous test implementations completed and successful full implementation undertaken for UAT

DSOR (Release 1-n)

YAF 10/12/15Developer not clear whats being deployed

Implementation Risk Assessment

A risk assessment has been undertaken for the Implementation Plan and selected deployment dates. (e.g. roll back)

ASOR (Release 1-n)

YAF 08/12/15 

TAD/Operaional Document

Documentation complete

Action: The Document must be copied to the Wiki

 

YAF 08/12/15no changes

System Design Specification (SDS)

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

ASOR (Final Release  / Handover)

YAF 08/12/15wiki updated

System Description Document

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

ASOR (Final Release  / Handover)

YAF 08/12/15wiki updated

Scalability/Load Testing

Adequate load testing has taken place. The results have been recorded and analysed to ensure that the application will cope with the anticipated load.

ASOR (Final Release  / Handover)

NAF 08/12/15not done

Performance

The application has been tested against stated performance criteria. Performance has been assured by user and support staff testing.

ASOR (Final Release  / Handover)

NAF 08/12/15N/A

Source Code

 

Source control must be checked out till go-live and checked-in after go live

Source code has been secured with SVN or other source control tool.

Action: ensure Production Branch created

Where code is provided by a third party (e.g. supplier) it has been established who is responsible to maintain source code

 

DSOR (Final Release  / Handover)

YAF 06/01/16

need a new production branch currently prod_1.1.x

production branch created with same name ie prod_1.1.x

Configuration Management Database

The relevant details regarding new or changed infrastructure components have been added to the CMDB in unidesk

ASOR (Release 1-n)

YAF 21/01/16to be  now added to cmdb  A1510-006

Change Control(s)

A Change & Release record  has been created in unidesk for the LIVE implementation request.

 Action: record unidesk number

ASOR / (Release 1-n)

YAF 08/12/15
C1510-004
SCE008
 

Test Log Review

A review of the test log (JIRA) has taken place to ensure all required actions have been completed.   If this is not the case, then confirmation on criticality of outstanding issues and action plan for resolution is required.

ASOR (Final Release  / Handover)

YAF 06/01/161 open jiras - to be done in January 2016 completed

Production Management Handover

Handover to Applications Management and Technology Management is completed or arranged and the teams are in position to support the application post deployment.

Action: record handover dates

ASOR (Final Release  / Handover)

YAF 08/12/15 

Support Accounts

Read access accounts or update current read access accounts have been set up for support staff(requires business owner approval)

ASOR (Final Release  / Handover)

YAF 08/12/15already exists

Password Manager (InfoKeep)

Password Manager Pro has been updated with all relevant account details including external supplier  accounts

ASOR (Release 1-n)

YAF 08/12/15 

Environment comparison

Database comparison between TEST and LIVE (might be required before and after go-live)

ASOR (Final Release  / Handover)

YAF 08/12/15N/A

Client requirements

Does the application have specific client requirements, such as JVM/JRE versions, JInitiator etc

If so have these requirements been raised with Desktop services

Wiki pages to be updated:

[1] https://www.wiki.ed.ac.uk/display/insite/Corporate+applications+with+client+based+requirements

[2] https://www.wiki.ed.ac.uk/display/insite/Client+side+requirements+for+corporate+applications

ASOR (Release 1-n)

YAF 08/12/15No change

Technologies

Is there any new software or technologies involved? (Y/N)

If yes state any additional actions taken to ensure adequate handover to the production support team

ASOR (Release 1-n)

YAF 08/12/15No change

Access outside University

By default all web based applications are accessible outside University without use of VPN etc Wiki list

If not accessible from outside University this needs to be approved by Production Management.

ASOR (Release 1-n)

YAF 08/12/15No change

Vendor Access Required

Does vendor require db/app access (Y/N)

If yes, ensure access details are in TAD

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Certificates

All changes to certificates or new certificates for this service have to be added to the certificate master list. The certificate master list is being managed by Applications Management This includes TEST and LIVE certificates and records type of certificate and expiry dates.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Deployment Date(s)

Agreed date has been confirmed that allows adequate time for completion of Acceptance Sign Off Review.

ASOR (Final Release  / Handover)

Y AF 08/12/1506/01/15

Deployment Resources

IS and business area resources required for deployment, including those needed for post implementation checking and sign off have been secured.

ASOR (Final Release  / Handover)

YAF 08/12/15 

Deployment Ownership

Responsibilities for managing the go-live, including: comms with service owner and end users, ensuring go live timescales are met, managing issues arising and managing comms between all teams involved in go live.

ASOR (Final Release  / Handover)

YAF 08/12/15

PM

Service Announcement(s)

A Service announcement has been raised with the agreed deployment date on the alert system:

 

http://reports.is.ed.ac.uk/alerts/

 

Service announcements should be raised by Project Manager 10 days before go live, but no later than 4 days.

ASOR (Release 1-n)

YAF 08/12/15short notice

Reporting and Analytics

New BI Universes or substantial changes to Universes/report offerings need to be documented in the Information Portal managed by GaSP.

https://www.wiki.ed.ac.uk/display/IP/Information+Portal+Home

ASOR (Release 1-n)

YAF 08/12/15N/A

Infrastructure checklist  - NO CHANGES

 

Component

Success Criteria

Project Stage Required (Agile)

OK (Y/N)Reviewed by (date)Outdstanding Actions (Who)

Technical Architecture/Operational Document(TAD)

Documentation complete and accurately reflects the environment subjected to UAT.

 

ASOR (Release 1-n)

YAF 08/12/15no changes to infrastructure or TAD

Security

All security requirements, e.g. SSL encryption, IP based restrictions firewall requirements have been specified, tested and implemented in LIVE

ASOR (Release 1-n)

   

User Accounts

     

Patching

Ensure that all applications have an agreed patching schedule and this schedule is agreed with service owners. Different technologies have different patching strategies:

Oracle, Windows, Linux

ASOR (Final Release  / Handover)

   

Start/Stop scripts

Are Server Start-up/Shutdown scripts in place?

Including start-up procedure documented, enabled and tested

ASOR (Release 1-n)

   

Ports

Port allocation file been updated:

 

https://www.wiki.ed.ac.uk/display/insite/Port+Allocation+on+Unix+Servers

ASOR (Release 1-n)

   

Backup and Recovery

All backups as noted in the TAD need to be confirmed operational.

 

A test recovery of user data needs to be done to validate the integrity of the recovery mechanism and process.

ASOR (Release 1-n)

   

DR Copy

DR copy to SECONDARY DB configured and tested (unless existing database which is already setup).

ASOR/Release1

   

Logs

For all logs the following is in place:

  • Logs are rotated and old logs are archived or deleted to ensure server space is not reached

  • In production only minimal levels of logging is switched on (debug may be adequate on DEV, but not on Production)

ASOR (Release 1-n)

   

 Support checklist

 

Component

Success Criteria

 Project Stage Required (Agile)

OK (Y/N)Reviewed by (date)Outdstanding Actions (Who)

Support Agreement (including any charging arrangements)

A support agreement OLA is in place for any new applications – including any hosting or support charges. Where external suppliers are involved an SLA should be in place as well.

 

Action: SLA  moved to wiki:

 

https://www.wiki.ed.ac.uk/display/insite/SLA+repository+-+Applications+Management

ASOR (Final Release  / Handover)

YAF 08/12/15 No change

Time Recording Code

A Time Recording code for the application, if required, has been confirmed and set up (in ASTA)

Action: Does application require a separate entry for business area in ASTA

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Disaster Recovery and Business Continuity

Appropriate DR/BC provision is in place and has been fully tested. Application DR/BC details have been transferred to the DR Portfolio and DR level (1, 2 or 3) has been agreed

ASOR (Release 1-n)

YAF 08/12/15No change

Test Environment

An adequate TEST environment has been established for the application which may be used by support to test future changes prior to releasing these in the LIVE environment.

ASOR (Release 1-n)

YAF 08/12/15No change

Hardware and Software Licensing

All required licensing is in place including maintenance/support arrangements with external suppliers.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Browser Compatibility

Browser compatibility has been tested and compatibility information updated

See

http://www.ed.ac.uk/schools-departments/information-services/services/computing/application-development/application-support/supported-web-browsers/browser-application

 for details

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Portal Compatibility

Portal compatibility, where required, has been confirmed the Portals Service Owner.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Help Desk

The new application is recognised with the UniDesk (A business contact queue is defined where initial calls are raised with)

ASOR (Final Release  / Handover)

YAF 08/12/15No change

User Guide Documentation

Appropriate documentation has been produced for users of the new application.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Training Material

Training material, if required, has been produced and is of an appropriate standard.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Demonstration or Walkthrough

Demonstration or walkthrough of the new application has taken place for other stakeholder.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

Web Sites and Other Document Sources

External and internal web sites have been reviewed to ensure that all application references are present, correct and up to date.

ASOR (Final Release  / Handover)

YAF 08/12/15No change

 

 

Project Info

Project
University Seminar Site Enhancements
Code
SCE008
Programme
SCE Portfolio Projects (OTHSCE)
Project Manager
Morna Findlay
Project Sponsor
Bob Fisher
Current Stage
Close
Status
Closed
Start Date
23-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Jan-2016
Category
Discretionary