Assessment Scorecard
|
Characteristic |
|
Mark |
Score |
|---|---|---|---|
|
Cost of Project - Costs must include all time/resource to be spent on the project and not just the dedicated project team. A total cost of ownership approach should be used which includes all project costs over 48 months including any recurring costs. |
£25m or over |
15 |
2 |
|
£10m or over |
7 |
||
|
£1m or over |
4 |
||
|
£0.5m or over |
2 |
||
|
Under £0.5m |
1 |
||
|
Impact on Staff and Students |
Direct impact on students and/or staff across the University |
4 |
4 |
|
Direct impact on students and/or staff across a College or Support Group |
3 |
||
|
Direct impact on students and/or staff across a School, organisational unit or other significant group |
2 |
||
|
Impacts only on some students and/or staff within the organisation |
1 |
||
|
Complexity |
High
|
4 |
|
|
Medium
|
2 |
2 |
|
|
Low
|
1 |
|
|
Reputational Impact on University if project gets into difficulties or is not delivered |
Potential for impact on international or UK profile |
4 |
4 |
|
Potential for impact on Scotland profile |
2 |
||
|
Potential for local impact |
1 |
||
|
|
Overall Project Score |
12 |
|
| Major Project? | Yes | ||
If Score is 10-19 the project is a “Major” project
If Score is <10 the project is a “Normal” project