Report for November 2019
- Report Date
- November 2019
Achievements this period
- DEV has been signed off, and Euclid has now been switched to new upgraded servers
- TEST servers: building and testing in progress
Issues
- Project Manager left the project in October (now working with Core systems).A new project manager was assigned in late November
- Re-planning in progress with project aiming to consider moving to LIVE on 11-DEC (https://secure.projects.ed.ac.uk/unpublished/project/sac080/issues/4) . It is now at risk as some of the team are absent now for 8 days as a result of industrial actions
Next Steps
- Replan and agree new dates
- TAD to be provided from Dev Tech to Tech Management
- LIVE Server to be requested from ITI
- TEST environment upgraded, signed off and on new servers
- TRN environment upgraded, signed off and on new servers
- LIVE environment upgraded, signed off and on new servers
| Stage | Milestone | Due Date |
|---|---|---|
| Integrate | TEST Environment Upgraded, Signed Off and on new servers | 06-Dec-2019 |
| Accept | TRN Environment Upgraded, Signed Off and on new servers | 09-Dec-2019 |
| Deliver | LIVE Environment Upgraded, Signed Off and on new servers | 11-Dec-2019 |
| Deliver | DUST Environment Upgraded, Signed Off and on new servers | 10-Jan-2020 |
| Deliver | Deployment Sign off | 20-Jan-2020 |
| Close | Decommissioning of all Environments | 23-Jan-2020 |
| Close | Closure | 14-Feb-2020 |
- Approved budget
- 105.0 days
- Activity this month
- 13.0 days
- Activity this year
- 49.0 days
- Activity to date
- 61.0 days
- Estimate to complete current year
- 34.0 days
- Estimate to complete future years
- 0.0 days