Report for September 2019

Report Date
September 2019

Achievements this period

  • All environments in place as requested
  • DEV Finish Up for two DEV servers required some more time as expected
  • Milestones were adjusted accordingly without affecting the Live Release date
  • Closing Date was brought forward for the end of 2019

Issues

  • DEV Built Phase required more time than expected and is delaying the completion of the Built stage

Next Steps

  • TAD to be provided from DevTech to TechManagement
  • DEV Built to be finished up and tested
  • TEST Built to be started
  • LIVE Server to be requested from ITI
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Has formal escalation taken place?
No
Activity
Approved budget
105.0 days
Activity this month
4.6 days
Activity this year
13.7 days
Activity to date
26.1 days
Estimate to complete current year
76.9 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS RedHat Operating System move to Centos
Code
SAC080
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Brandi Headon
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
26-Apr-2019
Planning Date
30-Aug-2019
Delivery Date
23-Mar-2020
Close Date
11-May-2020
Overall Priority
Normal
Category
Compliance

Documentation