- Report Date
- September 2019
Achievements this period
- All environments in place as requested
- DEV Finish Up for two DEV servers required some more time as expected
- Milestones were adjusted accordingly without affecting the Live Release date
- Closing Date was brought forward for the end of 2019
Issues
- DEV Built Phase required more time than expected and is delaying the completion of the Built stage
Next Steps
- TAD to be provided from DevTech to TechManagement
- DEV Built to be finished up and tested
- TEST Built to be started
- LIVE Server to be requested from ITI
- Approved budget
- 105.0 days
- Activity this month
- 4.6 days
- Activity this year
- 13.7 days
- Activity to date
- 26.1 days
- Estimate to complete current year
- 76.9 days
- Estimate to complete future years
- 0.0 days