- Report Date
- August 2019
Achievements this period
- TAD to be started
- One Virtual Machine in place to work on
- Project Brief and Planning was signed off and approved
- Deployment Date was agreed for the 7th November 2019 with the Business and is aimed for Delivery
Issues
- Environments are not in place yet
- Resource Bookings are not secured yet
- Change of End of Planning / Submission of the Project Brief Date
Next Steps
- TAD to be provided from DevTech to TechManagement in first week of September
- All servers to be secured for DUST, DEV, TEST, TRN for now
- LIVE Server to be requested Mid September
- Approved budget
- 105.0 days
- Activity this month
- 9.1 days
- Activity this year
- 9.1 days
- Activity to date
- 19.1 days
- Estimate to complete current year
- 87.2 days
- Estimate to complete future years
- 0.0 days