Report for August 2019

Report Date
August 2019

Achievements this period

  • TAD to be started
  • One Virtual Machine in place to work on
  • Project Brief and Planning was signed off and approved
  • Deployment Date was agreed for the 7th November 2019 with the Business and is aimed for Delivery

Issues

  • Environments are not in place yet
  • Resource Bookings are not secured yet
  • Change of End of Planning / Submission of the Project Brief Date

Next Steps

  • TAD to be provided from DevTech to TechManagement in first week of September
  • All servers to be secured for DUST, DEV, TEST, TRN for now
  • LIVE Server to be requested Mid September
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Has formal escalation taken place?
No
Activity
Approved budget
105.0 days
Activity this month
9.1 days
Activity this year
9.1 days
Activity to date
19.1 days
Estimate to complete current year
87.2 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS RedHat Operating System move to Centos
Code
SAC080
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Brandi Headon
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
26-Apr-2019
Planning Date
30-Aug-2019
Delivery Date
23-Mar-2020
Close Date
11-May-2020
Overall Priority
Normal
Category
Compliance

Documentation