Report for April 2019

Report Date
April 2019

Achievements this period

  • Project got approved
  • Initial Meeting took place and clarified that the Database Tier is out of Scope for this project
  • First steps and requirements were identified

Issues

  • n/a

Next Steps

  • Initial Analysis by DevTech will take place. Resources were requested and should be available referring to Resource Management.
  • Results will provide the foundation for planning, which is aimed to be completed by 31st May
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
0.4 days
Activity this year
0.5 days
Activity to date
0.0 days
Estimate to complete current year
55.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS RedHat Operating System move to Centos
Code
SAC080
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Brandi Headon
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
26-Apr-2019
Planning Date
30-Aug-2019
Delivery Date
23-Mar-2020
Close Date
11-May-2020
Overall Priority
Normal
Category
Compliance

Documentation