Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 AMBER 105.0 days 67.0 days 35.0
Content
Status
In Progress
Current Stage
Execute
Start Date
Friday, 26 April 2019
Planning Date
Friday, 30 August 2019
Delivery Date
Monday, 23 March 2020
Close Date
Monday, 11 May 2020
Project information
Project Code
SAC080
Programme
Student Systems Partnership SSP
Session
19/20
18/19
Organisational Unit
Student and Academic Support Group (SASG)
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Run
Funding Source
Sponsor funded
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students