June 2019
- Report Date
- June 2019
Achievements in Last Period
- Completed the executive summary for project board -Provided estimations of work for 1) software change, 2)migration to HECOS, 3) business change
- Detailed the implementation migration of JACS to HECoS and estimated resources
- Completed data governance and reviewed with Ops
Issues
-
Dates still not known: expected HESA to announce new dates in July 2019 (was May 2019)
-
Resource gaps highlighted to project board. Decision required following replanning work over 3 years and as per priority . At the moment no Developer secured apart from lead dev. BA gap too. Raised at programme level https://secure.projects.ed.ac.uk/unpublished/programme/sac/risks/44- and escalated to programme owner to clarify funding with GASP
- Dependencies with suppliers to address some of the issues raised:
- software release (Aug & Oct 2019)
- Tribal consultancy booked from July 2019 onwards
Note that 2nd stream - new data required to be captured at the next registration. PM secured and analysis work in progress see separate initiated project https://secure.projects.ed.ac.uk/project/sac078
Next Steps
- Replan work over 3 years and present priorities
- New go live date from HESA board expected in July: replan project/milestones accordingly
Milestones
Revised dates to be confirmed in July by HESA, new dates are tbc once work has been replanned over 3years
|
- Approved budget
- 240.0 days
- Activity this month
- 35.0 days
- Activity this year
- 152.0 days
- Activity to date
- 152.0 days
- Estimate to complete current year
- 17.0 days
- Estimate to complete future years
- 120.0 days
