May 2019
- Report Date
- May 2019
Achievements in Last Period
- System analysis progressing : aim to provide software estimation end June
- Secured BA to detail implementation migration of JACS to HECoS and estimate resources
- Progressed with data governance, being reviewed with Ops
Issues
-
Rescheduled dates still not known: expected HESA to announce new dates in July 2019 (was May 2019)
-
Analysis behind schedule due to sickness. Working towards getting all high priorities analysis completed and estimated for end June. Full analysis likely to complete early Aug.
-
Dev gap from July. No Developer secured apart from lead dev. BA gap too. Raised at programme level https://secure.projects.ed.ac.uk/unpublished/programme/sac/risks/44- and escalated to programme owner to clarify funding with GASP
- Dependencies with suppliers to address some of the issues raised:
- software release (Aug & Oct 2019)
- Tribal consultancy booked from July 2019 onwards
Note that 2nd stream - new data required to be captured at the next registration. PM secured and analysis work in progress see separate initiated project https://secure.projects.ed.ac.uk/project/sac078
Next Steps
- Progress with analysis and complete high level estimates
- Progress with detailed plan for migration to HECoS and estimates
- Progress with business change implementation and estimates
- Provide executive summary of estimates and resource plan
- Progress with user groups
- New go live date from HESA board expected in July: replan project/milestones accordingly
Milestones
Revised dates to be confirmed in July by HESA, new dates are tbc
|
- Approved budget
- 240.0 days
- Activity this month
- 22.0 days
- Activity this year
- 117.0 days
- Activity to date
- 117.0 days
- Estimate to complete current year
- 59.0 days
- Estimate to complete future years
- 113.0 days
