February 2019
- Report Date
- February 2019
Achievements in Last Period
- System analysis progressed and 2 d consulting with Tribal held with the project team
- Some progress on the constitution of the working groups
Issues
-
At risk: system analysis completion 22 Mar- Delay to resourcing (sickness, WSA, SIST upgrade) . To be reviewed. Following milestones/impact to be revisited at end of analysis
-
PM resource conflict with student experience plan https://secure.projects.ed.ac.uk/unpublished/project/sac077/issues/4 - Resource requested from other department
-
No Developer secured apart from lead dev. Likely required for April/May dependent on system analysis outcome
-
Business analyst secured, to work with Lesley on running the user groups, but limited availability before end March- Raised with her resource manager.
-
Go/no Go decision delayed
Note that 2nd stream - new data required to be captured at the next registration. PM secured and analysis work in progress see separate initiated project https://secure.projects.ed.ac.uk/project/sac078
Next Steps
- Progress with analysis
- Progress with detailed plan for migration to HECoS
- Progress with working user groups
- Feedback from HESA board about go/no go, impact to project delivery
Milestones
- Approved budget
- 240.0 days
- Activity this month
- 19.0 days
- Activity this year
- 36.0 days
- Activity to date
- 36.0 days
- Estimate to complete current year
- 172.0 days