December 2019

Report Date
December 2019

Achievements in Last Period

  • None as no resources onto the project for analysis or sytem changes, or PM
  • PM will restart assignment on the project from Feb once other resources are available

Issues

Note that 2nd stream - new data required to be captured at the next registration. PM secured and analysis work in progress see separate initiated project https://secure.projects.ed.ac.uk/project/sac078

Next Steps​

  • Complete mode of study design from Feb 2020 post PCIM work
  •  Start build (population) in Feb 2020, with 2nd developer
  • Plan work with new PM, incl clarify what changes are required to use standard SITS (and not the IS programme workaround) to complete statutory returns in 20/21  

Milestones 

Revised dates  confirmed in July by HESA, new dates replanned over 3 years

  • Implementation to HECoS by end Jan 20, so that statutory returns for 19/20 is done using legacy systems with new HECoS codes 
  • TBC -20/21 likely 3 statutory returns using legacy returns (i.e. keep using current data model. Impact: will need ability to churn data volume and quality) .
  • TBC- 21/22 3 new statutory returns 
Project Status
RAG Status
Time
RED
Cost
AMBER
Scope
AMBER
Overall
RED
RAG Commentary
Several issues: -1) the Business Analyst who has left the project (conflict with Core Systems) in Oct has not been replaced. Impact to data quality analysis to remove barrier to future returns. Plan to resolve: Request for her return in February has been escalated by sponsor to CIO/USG deputy secretary. - 2) Constraints Dec resource. Impact: Delay in starting build a. Plan to resolve: 2nd Dev resource has been secured from Feb 20. -3) Lead developer has been conflicted with PCIM work over Dec/Jan. Impact of 1, 2 & 3: project is delayed, development and system changes activities were suspended over Dec and Jan . Plan to resolve: Secure return of conflicted resources but additional resources amy be needed to meet statutory requirements for 2020/21 returns. In addition, there is also uncertainty about the HESA requirements and when this will be communicated. This risk is on the need for future additinal scope. Plan to resolve: Current scope of work for 19/20 will prepare foundation for both system and data quality.
Change Status
Has formal escalation taken place?
Yes
Escalated to
CIO/USG deputy secretary
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Futures - Requirements Analysis & Implementation
Code
SAC077
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Victoria Weinsberg
Project Sponsor
Lisa Dawson
Current Stage
Design
Status
In Progress
Project Classification
Run
Start Date
26-Nov-2018
Planning Date
21-Dec-2018
Delivery Date
23-Oct-2022
Close Date
01-Dec-2022
Programme Priority
3
Overall Priority
Higher
Category
Compliance

Documentation