November 2019
- Report Date
- November 2019
Achievements in Last Period
- The option we went with was to do Coverage/Population, Audit and Study Mode this Academic Year (resource permitting).
- Completed Coverage/Population and Audit design (technical requirements articulated for starting the build). Still on track but will need time to analyse and spec detailed requirements for Mode of Study for new developer starting in February.
- Resource gaps highlighted to project board. Agreed to allocate 2nd developer to project from Feb 2020
Issues
-
The Project Manager and the experience BA have left the project to work on Core Systems https://secure.projects.ed.ac.uk/unpublished/project/sac077/issues/9 and have not been replaced yet
-
Suspend project Dec/Jan. Lead developer conflicted with PCIM work (Service Excellence) for 6 weeks (Dec 2019 and Jan 2020): https://secure.projects.ed.ac.uk/unpublished/project/sac077/issues/10
Note that 2nd stream - new data required to be captured at the next registration. PM secured and analysis work in progress see separate initiated project https://secure.projects.ed.ac.uk/project/sac078
Next Steps
- Complete mode of study design from Feb 2020 post PCIM work
- Start build (population) in Feb 2020, with 2nd developer
Milestones
Revised dates confirmed in July by HESA, new dates replanned over 3 years
- Implementation to Hecos by end Jan 20
- TBC -20/21 likely 3 returns using legacy returns (keep using current data model. Impact: will need ability to churn data volume and quality)
- TBC- 21/22 3 new returns
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days