November 2018

Report Date
November 2018

Achievements in Last Period

  • project initiated

Issues

  • 1st stream: new statutory framework- no business analyst is available for now. The BA planned for this work is not available prior to Feb (Funding handover and live support, and then SITS upgrade regression test on fees/funding in Jan)

  • 2nd stream - new data required to be captured at the next registration. The scope of initial re-enrolment for continuing students work requires to start the course re-enrolment process in Jan, for build in Feb for deployment in June. This stream needs to be prioritised over current work or require a new BA. 

Next Steps​

  • secure resources for both streams
  • progress with brief and governance membership

Milestones

provisional tbc at end of planning

In three months

(March 2019)

  • Scoping work to understand the size of the project completed
  • Resource requirements identified and allocated
  • Identify the data custodians and stewards who are responsible for each part of the record
  • Project board established
  • Working group established

In six months (June 2019)

  •  Re-enrolment process set up for 2019/20 intake
  •  Change requirement task and finish groups active

 

The project will then inform the work required for 19/20:

In nine months (Oct 2019)

  •  System developed for testing

In twelve months

  •  System tested so we can meet the mandatory test required for  January 2020
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
Amber as a) BA resources to start project have not been secured, b) scope:There is emerging additional work: new data to embed within new registration process
Change Status
Has formal escalation taken place?
Yes
Escalated to
programme sponsor - seeking clarification about priority and additional funding as part of the SSP programme of work
Activity
Approved budget
100.0 days
Activity this month
1.0 day
Activity this year
99.0 days
Activity to date
1.0 day
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Data Futures - Requirements Analysis & Implementation
Code
SAC077
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Victoria Weinsberg
Project Sponsor
Lisa Dawson
Current Stage
Design
Status
In Progress
Project Classification
Run
Start Date
26-Nov-2018
Planning Date
21-Dec-2018
Delivery Date
23-Oct-2022
Close Date
01-Dec-2022
Programme Priority
3
Overall Priority
Higher
Category
Compliance

Documentation