Impact

Priority and Funding

Compliance – priority Higher - Core funded (SSP Ring Fenced)

 

Impact and Dependencies

This project will impact the Scottish Funding Council returns and Teaching Load by providing the FTE for each student.

Dependencies

  • The Data Futures requirements remaining relatively stable throughout the period of analysis.  HESA assure us that the Coding Manual will remain stable from September 2018.
  • Tribal providing detail of their proposed solution to enable us to assess the degree that their software can provide us with an off the shelf solution.  We currently have specifications and the software is being delivered through software updates from August 2018, and through the annual SITS software double upgrade (SAC076), with go live planned for March 2019
  • The Work and Study Away project (SAS004) within Service Excellence will provide the means to identify off venue activities of the students. Although the WSA project will provide this going forward, it will not contain historic data.  It will therefore only have data for students who apply for Work or Study Away following the implementation of the new system. The impact for the statutory returns will need to get off venue data for the start of 19/20 as it is now and change the source of data when WSA  project is implemented.
  • The PCIM (SAS010) within Service Excellence will provide how the programme and course information is held in the future. This will not impact this project as the PCIM implementation is currently planned post Data Futures, but there will likely be changes post Data Futures implementation.
  • Be able to return a HESA student return 2018/19 in the old format but post Aug 2019
  • Dependency from GaSP: agreeing the  new HECoS coding for courses with schools (programmes already recoded using HECoS codes)
  • Beta testing finishes in Sep 2019

 

 

Project Risks

Ref

Title-Description

 

Impact

Probability

Mitigation

Risk Owner

1

The HESA Data Futures requirements may change between the start and end of the project

High

 

Low

Manage the information change relating to Data Futures (i.e use the Hesa website and contact with other  universities)  

Paula Webster

2

HESA have not firmed up significant processes such as the change processes and the quality rules (i.e. the HESA imposed rules used in the external collection system) within the timescales of this project

 

Med

Medium

Accept and work with HESA changes. Review resources accordingly.

Paula Webster

3

There is a risk the SSP resources are not fully committed 

High

Medium

Project has been prioritised and resources allocated as follows- Business Lead and Lead Developer will start with the initial system analysis. BA for the analysis/process review. BA for the migration plan.

To be reviewed as initial analysis is progressing. Consider securing consultancy from Tribal or recruit new Dev

 

Franck Bergeret

4

There is a risk the analysis and design are taking longer. Some institutions have started such work a year ago.

High

Medium

Reallocate resource from discretionary projects within the SSP programme or recruit extra resource.

Checkpoint/ review and prioritise over other SSP work if required

Franck Bergeret

5

Other internal projects (eg Working and Study Away) develop solutions which do not meet the requirements for Data Futures

 

Medium

Medium

Review the requirements

 

SSP Developer doing initial analysis is also Dev lead on WSA system implementation. Feed into the requirements workshops planned for Jan/Feb 2019

Morag Iannetta

6

Tribal is unable to provide sufficient detail about their proposed solution to enable us to make an assessment on the suitability of their software

 

High

Low

Tribal Roadmap due Aug 2019.

Business lead to attend data working group every quarter.

Lesley Elliot

 

7

Dependency on small pool of staff with requisite business knowledge

High

Medium

Increasing documentation and work shadowing during the process to spread knowledge

Support from lead business analyst and business lead

Paula Webster

8 There is a dependency on HESA migrated data from existing HESA returns to the new Data Futures structure. As a result data will be rejected by HESA, and no return is submitted- High  Medium

Accept and work with/investigate  HESA changes.

Review resources accordingly.
Paula Webster

Project Info

Project
Data Futures - Requirements Analysis & Implementation
Code
SAC077
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Victoria Weinsberg
Project Sponsor
Lisa Dawson
Current Stage
Design
Status
In Progress
Project Classification
Run
Start Date
26-Nov-2018
Planning Date
21-Dec-2018
Delivery Date
23-Oct-2022
Close Date
01-Dec-2022
Programme Priority
3
Overall Priority
Higher
Category
Compliance

Documentation

Plan