Report for January 2017
- Report Date
- January 2017
Achievements this period
- Sign off DEV upgrade
- improvements identified after DEV upgrade which reduced duration of TEST upgrade
- TEST upgrade completed
Issues
- MENFIX step in 9.2.0 upgrade in test took 40 hours - resolved by deleted old audit records in TEST database to reduce duration of MENFIX steps in TEST and then re-adding records.
- issues with DEV streams means this work has to be redone (resolved)
Next Steps
- Project to be re-estimated.
- UAT underway in TEST
- sign off TEST upgrade
Milestones
| 03-Mar-2017 | Sign off TEST upgrade | ||
| 06-Mar-2017 | Upgrade TRN | ||
| 18-Mar-2017 | Upgrade LIVE | ||
| 01-Apr-2017 | Fallback date LIVE upgrade | ||
| 14-Apr-2017 | Deployment Sign off | ||
| 25-Apr-2017 | Refresh TEST from LIVE | ||
| 02-May-2017 | Upgrade DUST | ||
| 19-May-2017 | Close |
RAG Status
Project is GREEN
- Approved budget
- 210.0 days
- Activity this month
- 44.0 days
- Activity this year
- 103.0 days
- Activity to date
- 103.0 days
- Estimate to complete current year
- 116.0 days
- Estimate to complete future years
- 0.0 days