Report for April 2017
- Report Date
- April 2017
Achievements in Last Period
- Continued setting up of progression/award rules
- Supported schools in use of enrolment maintenance tools and preparation for boards
- Developed enhancements to student processing screens
- Developed training on progression and award board processing
Resolved issues
- Issue 2: Change to Brief sign off milestone.
Open Issues
- Issue 12: Withdrawal of Deploy CCAM/APT integration milestone
- Issue 13: Change to deployment of enhanced processing for Reassessments
Next Steps
- Complete performance testing on award and progression rules
- Deploy award and progression rules
- Support schools in the exam board period
- Develop and fixes as required to support exam boards
Milestones
| Target Date |
Previous Date | Title | Stage | Complete | |
|---|---|---|---|---|---|
| 04-Apr-2017 | No date available | Deploy enhancements for Semester 2 boards | Deliver | No | |
| 02-May-2017 | 16-Mar-2017 | Complete performance testing | Build | No | |
| 02-May-2017 | 09-Mar-2017 | Deploy progression and award rules for 2016/17 Schools' Programmes | Build | No | |
| 20-Jul-2017 | 26-Jan-2017 | SMART decommissioned | Build | No | |
| 20-Jul-2017 | No date available | Deploy CCAM/APT integration | Build | Withdrawn | |
| 21-Jul-2017 | No date available | Complete review of Semester 2 exam boards | Accept | No | |
| 03-Aug-2017 | No date available | Deploy enhanced processing for Reassessments | Deliver | No | |
| 03-Aug-2017 | No date available | Deploy enhancements to student and staff views | Deliver | No | |
| 05-Sep-2017 | 27-Mar-2017 | Project closure | Close | No |
- Approved budget
- 325.0 days
- Activity this month
- 17.0 days
- Activity this year
- 262.0 days
- Activity to date
- 262.0 days
- Estimate to complete current year
- 63.0 days
- Estimate to complete future years
- 0.0 days