- Report Date
- November 2016
Achievements in Last Period
- Completed and deployed processing for publication and view of in-course assessment marks
- Continued development of marker identification and double marking.
- Continued DPT analysis and start development
- Continued transition planning (all phase 2 schools complete 5/12)
- Initial prototyping of new DPT maintenance tool
- Presentations to Boards of Examiners briefing sessions in 3 colleges
- Developed and deployed barcodes for exams
Resolved issues
Open Issues
Next Steps
- Complete brief
- Support schools in preparation for January exam boards
- Complete transition planning with group 3 schools
- Complete development and deploy double marking and marker identification
- Collate and present DPT findings
- DPT maintenance design and first cut development
- Approved budget
- 250.0 days
- Activity this month
- 42.0 days
- Activity this year
- 113.0 days
- Activity to date
- 113.0 days
- Estimate to complete current year
- 137.0 days
- Estimate to complete future years
- 0.0 days
This article was published on