Report for October 2016

Report Date
October 2016

Achievements in Last Period 

  • Supported MSc & MBA Award boards (pilot)
  • Deployed support for Pass/Fail courses  (release 18)
  • Development and initial deployment for publication and view of in course assessment marks 
  • Development work for markers and double marking
  • Started DPT analysis 
  • Started schoo visits for transition plannign for rest of 2016/17

Resolved issues

None

Open Issues

Next Steps

  • Complete brief
  • User testing and deployment of publication and view of in-course assessment marks
  • Complete development and deployment of marker identification and double marking.
  • Complete DPT analysis and start development
  • Complete transition planning
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project is amber because the brief has not been completed/signed off. This project is a continuation of the works started by SAC034 and planned developments have been shared with the project sponsor and steering group.
Change Status
Activity
Approved budget
250.0 days
Activity this month
25.5 days
Activity this year
71.0 days
Activity to date
71.0 days
Estimate to complete current year
179.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression
Code
SAC057
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
01-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
26-Jan-2018
Programme Priority
1
Overall Priority
Higher
Category
Discretionary

Documentation