Report for October 2016
- Report Date
- October 2016
Achievements in Last Period
- Supported MSc & MBA Award boards (pilot)
- Deployed support for Pass/Fail courses (release 18)
- Development and initial deployment for publication and view of in course assessment marks
- Development work for markers and double marking
- Started DPT analysis
- Started schoo visits for transition plannign for rest of 2016/17
Resolved issues
None
Open Issues
- Issue 2: Change to Brief sign off milestone
Next Steps
- Complete brief
- User testing and deployment of publication and view of in-course assessment marks
- Complete development and deployment of marker identification and double marking.
- Complete DPT analysis and start development
- Complete transition planning
- Approved budget
- 250.0 days
- Activity this month
- 25.5 days
- Activity this year
- 71.0 days
- Activity to date
- 71.0 days
- Estimate to complete current year
- 179.0 days
- Estimate to complete future years
- 0.0 days