Organisation

Work/Task Breakdown

- From the Technical review already completed by Tribal, use the written report to make changes - Apps Man (SSP to assist with testing)

- Implement SITS changes already recommended by Tribal - SSP

- Conduct a software review -Tribal, outcome: written report

- Implement software review recommendations (SSP)  

 

Load testing:

- Prioritise key processes during start of term -SSP/Operations-Done

-Detail the tasks being done by users within each of the process and set acceptable expected performance- Operations

-Technical review of the load testing: feasibility, tools, estimate-SSP/DevTech

- if above approved: write and develop load test scripts, and create load test framework-SSP/DevTech

- Carry out  load tests and write up results and recommendations

- Implement quick wins recommendations

 

 

Resources Skills and Cost

Detailed cost is detailed in in the 3 point estimates below.

Skills are among SSP: Developpers/ BA/Testers, DevTech and IS Apps Man. 

 

Project Governance

 

Project Info

Project
EUCLID Performance and Load Testing
Code
SAC055
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
07-Jul-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Feb-2017
Programme Priority
1
Category
Discretionary