Organisation
Work/Task Breakdown
Tasks | Deliverables | Owners |
Project Management | Project authorisation, Planning and Project documents. Communication and coordination with stakeholders. Manage project, sign off, resources, budget, risks, issues and reporting. | IS Project Services for the IS Strands Student Systems Operations for Dashboard related development work, implementation and communication with the users |
Analysis/Design | 1.Application Data Architecture doc (ADA) and System Design Specifications doc (SDS) 2.Technical Architecture Document TAD | 1.Student Systems Partnership SSP, Review with Dev Tech 2.Other IS Apps-Dev Tech |
Build It-IS Strand-Data Architecture | New Student Data Hub | IOther IS Apps-S Dev Tech Other IS Apps- Dev Team |
Build It-IS Strand-Data capture and transfer | 1.Deliver proof of concept for Webi report nightly refresh, and Dashboard refreshing automatically Webi report. 2.Data Capture: new data mart for course survey data Evasys 3.EUCLID/evision changes 4.Data transfer to a schema to feed BIS 5.Support data transfer
| 1. Service Management/Other IS Apps 2. SSP/Other IS Apps-Dev Team 3. SSP 4. SSP/Other IS Apps 5. Dev Tech |
Build It-IS Strand-BIS |
Build new BIS Universes for Evasys Enhance existing Universes STUDMI, Programme and Admission
|
Other IS Apps-Dev Team
|
Build It-Operations strand- Dashboards implementation |
1. Dashboard software implementation 2. Build Webi reports and dashboards 3. Publication
| 1. Service Management 2. Student Systems Operations 3. Service Management/Student Systems Operations |
Check it | 1.EUCLID/evision changes 2.Data capture and transfer
| 1.SSP/Other IS Apps 2.Student Systems Operations
|
Check it
| -BIS Universes -Webi reports and dashboards | Student Systems Operations |
Operations strand- Communication/engagement with users |
Establish dashboard community
| Student Systems Operations |
Document & handover | 1. Technical Architecture Document TAD 2. SITS Implementation plan 3. Data mart/ BIS Universes 4. Handover to IS Production for BIS/datamart 5. Handover to Service Management for supporting dashboards | 1. Dev Tech 2. SSP 3. SSP/Other IS Apps-Dev Team 4. Apps Man/Other IS Apps-Dev Team, Dev Tech/SSP 5.Operations/Service Management |
Deploy | Incremental deployments 1.IS Strands 2.Dashboards | 1. SSP/Dev Tech/Dev Team / Apps Man 2. Dev Tech/Apps Man/Operations |
Close It | Closure Review | IS Project Services/Operations |
Resources Skills and Cost
Resource IS skills have been identified following the SDS and estimation meeting:
- Service Management/IS to confirm publication proof of concept, to support the dashboards
- Data Architecture Technical Lead-Dev Tech: TAD, set schema , and support DataMart/BIS build as a percentage of build effort
- SITS/SSP developer and SSP testing
- BIS developers for data transfer and BIS work, peer testing - BIS Integration tester: resources and skills within Operations
- Oracle developer for manual script to extract and transform data from Evasys and SITS
- Dashboard design and build: resources and skills within Operations
- Production coordinators to support
- Project Management/SSP
It has been estimated as a Medium/Large project
The project is estimated at a total of 194 IS Apps days (180d 15/16, 14d 16/17)
There is additional SSP funding for the Other IS Apps effort: 116d. Plus the cost for using Rob as SSP BI expert
There is additional effort from SSP Tester and from Student Systems Operations.