Report for September 2016

Report Date
September 2016

Achievements in this reporting period:

  • None

 

Resolved issues:

 

Open issues:

 

Next Steps:

  • Obtain signoff for amended closure report 
Target dateTitle
7-Oct-2016Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
402.0 days
Activity this month
1.0 day
Activity this year
2.0 days
Activity to date
421.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Continuous Improvements
Code
SAC043
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Karen Osterburg
Project Sponsor
Barry Neilson
Current Stage
Close
Status
Closed
Start Date
03-Aug-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Oct-2016
Programme Priority
2
Category
Discretionary