July 2015
- Report Date
- July 2015
Achievements in last period
- Met with users from pilot schools for user acceptance.
- Completed Development.
- Testing completed.
- DSOR completed
Issues
- n/a
Next Steps
- Delivery
- Closure report
Milestones
31-Jul-2015 | |
18-Sep-2015 | |
30-Sep-2015 |
- Approved budget
- 97.0 days
- Activity this month
- 11.0 days
- Activity this year
- 81.0 days
- Activity to date
- 81.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 5.0 days