Report for May 2015

Report Date
May 2015

Achievements in Last Period

  • Sessions with Pilot schools demoing software built to date
  • Agreed list of programmes/courses to be included in the pilot
  • Minimum product for assessment set up almost complete
  • Minimum product for mark entry almost complete
  • Started universe design for assessment reporting
  • Strand 1 support - couple of small fixes & enhancements
  • School visits to see live processes during exam times

 

 

Issues

 

Next Steps

  • Complete minium product build for July testing
  • Tribal consultancy to assist with progression/award set up
  • School visits to witness boards
  • Arrange testing with pilot users

 

Target dateTitle
19-Jun-2015Final iteration complete for strand 2 end-to-end testing
31-Jul-2015End-to-end testing complete for strand 2 pilot
06-Aug-2015Deploy first cut pilot code to LIVE
07-Aug-2015Pilot go/no go
14-Aug-2015Checkpoint for 2015/16 work
29-Jul-2016Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
440.0 days
Activity this month
40.7 days
Activity this year
333.6 days
Activity to date
333.4 days
Estimate to complete current year
105.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary