Report for May 2015
- Report Date
- May 2015
Achievements in Last Period
- Sessions with Pilot schools demoing software built to date
- Agreed list of programmes/courses to be included in the pilot
- Minimum product for assessment set up almost complete
- Minimum product for mark entry almost complete
- Started universe design for assessment reporting
- Strand 1 support - couple of small fixes & enhancements
- School visits to see live processes during exam times
Issues
- Engagement with Tribal for product enhancments: https://www.projects.ed.ac.uk/project/sac034/issues/21
Next Steps
- Complete minium product build for July testing
- Tribal consultancy to assist with progression/award set up
- School visits to witness boards
- Arrange testing with pilot users
Target date | Title |
---|---|
19-Jun-2015 | Final iteration complete for strand 2 end-to-end testing |
31-Jul-2015 | End-to-end testing complete for strand 2 pilot |
06-Aug-2015 | Deploy first cut pilot code to LIVE |
07-Aug-2015 | Pilot go/no go |
14-Aug-2015 | Checkpoint for 2015/16 work |
29-Jul-2016 | Close |
- Approved budget
- 440.0 days
- Activity this month
- 40.7 days
- Activity this year
- 333.6 days
- Activity to date
- 333.4 days
- Estimate to complete current year
- 105.9 days
- Estimate to complete future years
- 0.0 days