Report for April 2015

Report Date
April 2015

Achievements in Last Period

  • Full rollout plan (2015/16-2017/18) approval by CSPC steering group
  • Assessment setup build
  • Mark entry build build 
  • Special Circumstances build 
  • Fixed performance issues for strand 1
  • Presented the progression project at Board of Examiners briefings
  • Establish requirements for course board reporting

Issues

We had the following issues which impacted on progress of strand 2 build, however this should not impact the minimum deliverable for July testing.

19Days lost to sickness
20Days lost to investigation of performance issues...

 

Next Steps

  • Demo software build to date with pilot schools
  • Agree definitive list of programmes/courses to be included in the pilot
  • Complete Assessment setup build and test
  • Complete Mark entry build and test  
  • Complete Special Circumstances build  and test
  • Develop universe for board reporting
  • Document progression and award rules for pilot programmes
  • Define view of progression and document process for set up and validation of progression rules
  • Support any strand 1 LIVE issues 

 

Target datePrevious dateTitle
19-Jun-201519-Jun-2015Final iteration complete for strand 2 end-to-end testing
31-Jul-201531-Jul-2015End-to-end testing complete for strand 2 pilot
06-Aug-201506-Aug-2015Deploy first cut pilot code to LIVE
07-Aug-201507-Aug-2015Pilot go/no go
14-Aug-201514-Aug-2015Checkpoint for 2015/16 work
29-Jul-201629-Jul-2016Close

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
440.0 days
Activity this month
49.0 days
Activity this year
293.0 days
Activity to date
293.0 days
Estimate to complete current year
145.0 days
Estimate to complete future years
350.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary