Report for March 2015

Report Date
March 2015

Achievements in Last Period

  • Completed UAT for strand 1 (30 users from across the University)
  • Made changes in reponse to UAT feedback, improved student self-service 
  • Handover and deployed strand 1 (project team will be supporting software through exam period to end June) 
  • Analysis of pilot courses
  • Document detailed SITS software issues that will necessitate workarounds for pilot and raised with Tribal
  • Completed technical analysis of mark entry and started development
  • Prepared full rollout plan (2015/16-2017/18) for presentation and approval CSPC steering group on 1 April
  • Gathered initial requirements for Special Circumstances processing
  • Completed presentations to senior staff in Schools and Colleges
  • Joint breifing communication sessions with Academic Services to 110+ staff across the University

Issues

Next Steps

  • Strand 2 plan and rollout to be approved by steering group, budget reviewed.
  • Review likely work for 2015/16.
  • Assessment setup build
  • Mark entry build
  • Document progression and award rules for pilot programmes
  • Build view of progression and document process for set up and validation of progression rules
  • Special Circumstances build  
  • Establish requirements for course board reporting
  • Support any strand 1 issues

 

Milestones

Target dateTitle
01-Apr-2015Strand 2 complete Foundation phase & review project budget
02-Apr-2015Checkpoint for 2015/16 work
09-Apr-2015Strand 1: Deploy student functions and enable staff processing.
19-Jun-2015Final iteration complete for strand 2 end-to-end testing
23-Jul-2015Deploy first cut pilot code to LIVE
04-Aug-2015End-to-end testing complete for strand 2 pilot
07-Aug-2015Pilot go/no go
 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Assessment & Progression in SITS
Code
SAC034
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Chris Giles
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Start Date
12-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Apr-2017
Programme Priority
1
Overall Priority
Normal
Category
Discretionary