Report for February 2015
- Report Date
- February 2015
Achievements in Last Period
- Strand 2 outline plan agreed by Steering group
- Continued build and test for strand 1
- Demo strand 1 to user groups
- Some UAT for strand 1 (to be completed March)
- Formulate detailed training & comms plan for strand 1
- School/College briefings with senior academic and administrative staff (to complete first week in March)
- Meetings with school representatives for pilot
- Established framework for strand 2 assessment set up and mark entry workflows
Issues
- None
Next Steps
- Complete UAT for strand 1
- Handover and deploy strand 1 (project team will be supporting software through exam period to end June)
- Formally agree School/programme/courses to include in pilot (CSPC to sign off)
- Document detailed SITS software issues that will necessitate workarounds for pilot and raise with Tribal
- Technical analysis mark entry and build prototype : with pilot school consultation
- Build view of progression and document process for set up and validation of progression rules
- Produce documented end to end process for a number nominated pilot programmes (using out the box software)
- Produce school rollout plan for 2015/16 - 2017/18
- Requirements and build to support recording of Special Circumstances
Milestones
12-Mar-2015 | Strand 1 Acceptance sign off |
19-Mar-2015 | Strand 1 Deployment |
01-Apr-2015 | Strand 2 complete Foundation phase & review project budget |
02-Apr-2015 | Checkpoint for 2015/16 work |
19-Jun-2015 | Final iteration complete for strand 2 end-to-end testing |
23-Jul-2015 | Deploy first cut pilot code to LIVE |
04-Aug-2015 | End-to-end testing complete for strand 2 pilot |
07-Aug-2015 | Pilot go/no go |
- Approved budget
- 400.0 days
- Activity this month
- 46.2 days
- Activity this year
- 175.0 days
- Activity to date
- 175.0 days
- Estimate to complete current year
- 226.0 days
- Estimate to complete future years
- 0.0 days