January report
- Report Date
- January 2015
Achievements in Last Period
- Continuation build of strand 1 progression processing
- Developed scope strand 2
- Further workshops with schools to assess for 2015/6 pilot
- Re-estimate of project resource required
- Meetings with schools to showcase development and get feedback
- Briefings arranged with senior academic and administrative staff (Feb and first week in March)
Issues
- None
Next Steps
- Sign off strand 2 Foundations through Steering group
- Complete build & test of strand 1
- User acceptance test of strand 1
- Formulate detailed training & comms plan for strand 1
- Technical investigation of options for mark entry (strand 2)
- Analysis of assessment set up and mark entry
- Analysis and definition of progression rules for pilot schools
- Continued consultation and communication to schools through briefings and workshops
Milestones
18-Feb-2015 | Strand 1 Acceptance sign off |
20-Feb-2015 | Strand 2 complete Foundation phase & review project budget |
05-Mar-2015 | Strand 1 Deployment |
02-Apr-2015 | Checkpoint for 2015/16 work |
19-Jun-2015 | Final iteration complete for strand 2 end-to-end testing |
23-Jul-2015 | Deploy first cut pilot code to LIVE |
04-Aug-2015 | End-to-end testing complete for strand 2 pilot |
07-Aug-2015 | Pilot go/no go |
- Approved budget
- 400.0 days
- Activity this month
- 36.3 days
- Activity this year
- 128.8 days
- Activity to date
- 128.8 days
- Estimate to complete current year
- 270.5 days
- Estimate to complete future years
- 0.0 days